November 2026 Construction Update
Construction Activities During October Geothermal horizontal piping and vault installation Fine grading and binder for West/North roadways Academic Wing sheathing, AVB, and masonry continued Community Wing exterior metal framing, sheathing, AVB, and blocking began. Roofing continued Academic Wing Stair A structural steel installation Academic Wing interior metal framing and MEP rough installations continued on 1st/2nd floor Community Wing under slab utilities continued Gymnas


October 2026 Construction Update
Construction Activities During September •Structural steel completed with Topping Off Ceremony •Community Wing interior foundations •Under slab utility work continued in Community Wing •Community Wing slab on deck poured on 2nd floor •Community Wing roofing work began •Academic Wing interior metal framing and MEP rough installations continued on 1st/2nd floor •Academic Wing exterior vapor barrier and masonry began •Geothermal horizontal connections and testing started •Subgra


September 2026 Construction Update
Click the links below for a recap of the September 2, 2026, Topping Off Ceremony: BCAT Full Ceremony Video BCAT News Feature


Steel Topping Off Ceremony
WEDNESDAY, SEPTEMBER 2, 2026 | 1:00 PM | FOX HILL ROAD, BURLINGTON, MA The Town of Burlington is pleased to announce the Steel Topping Off Ceremony for the new Fox Hill Elementary School. Members of the School Building Committee, the Massachusetts School Building Authority, Town Officials, students, and faculty will be in attendance to celebrate this important milestone. EVENT PROGRAM Welcome & History – Melissa Massardo Remarks – Superintendent Eric Conti, Principal Davi