November 2026 Construction Update

2 days ago
1 min read

Construction Activities During October

  • Geothermal horizontal piping and vault installation

  • Fine grading and binder for West/North roadways

  • Academic Wing sheathing, AVB, and masonry continued

  • Community Wing exterior metal framing, sheathing, AVB, and blocking began. Roofing continued

  • Academic Wing Stair A structural steel installation

  • Academic Wing interior metal framing and MEP rough installations continued on 1st/2nd floor

  • Community Wing under slab utilities continued

  • Gymnasium slab on grade was poured


Upcoming Construction Activities in November

  • Subgrade/gravel East fields and paved area

  • Generator pad installation

  • Window installation at Academic Wing

  • Roofing work to continue at high/low roofs on Community Wing

  • Exterior metal framing, sheathing, AVB, masonry, and sunshade bracket installation to continue at Community Wing

  • Overhead/in wall rough MEP and interior metal framing installation to continue in Academic and Community Wing

  • Underground utilities complete and final slab on grade pours at Community Wing


Please note that work will continue on Veterans Day (Wed 11/11) if necessary  


 
 